I intend to restart work on this project on March 15th and I'm posting a timetable below of the types of work that will be going on this year. I will try and keep the timetable up-to-date with changes that arise from the building progress or for any other reasons.
Dates: ( working on most days during the period) 
 | 
  
Type of work 
 | 
  
Number of POOSHers needed,  
 | 
 
March 15  - March 29 
 | 
  
Carpentry:  cutting and
  part-assembling baseplate, wallplate, window boxes temporary roof . 
Put cover on bale shelter 
 | 
  
1 - 2 
 | 
 
April 7 – May 8 
 | 
  
Bricklaying: Constructing stem wall with recycled brick, flint and
  lime mortar. 
Carpentry: completing temporary propped roof 
Straw delivery 
Prepare hazel pins 
Scaffolding 
 | 
  
1 - 4 
 | 
 
May 26 – June 8 
 | 
  
Wall-raising (bales) 
Wallplate assembled 
Wall compression 
 | 
  
4 - 8 
 | 
 
June 9 – June 23 
 | 
  
Get the roof on! 
 | 
  
1 - 4 
 | 
 
July 1 – 20 
 | 
  
Overrun period 
 | 
  
?? 
 | 
 
July 29 – Aug 12 
 | 
  
Lime Plastering 
 | 
  
1 – 8 
 | 
 
Aug 26 – Sep 30 
 | 
  
Lime & Clay plastering 
 | 
  
1 - 8 
 | 
 
Calendar View:
The normal pattern of work will be to do some building on 4 weekdays and Saturdays during the highlighted periods above, and to have Sunday and one weekday off. Maybe.
If you would like to come and lend a hand over the summer, please get in touch now via the POOSH network. My project is listed there at http://thepoosh.org/buildproject/richard-roberts/strawbale-workshop, and it is currently the only project in North Norfolk listed on the POOSH project map. (Please do NOT contact me via this blog; I may not see your message.)